In the frame

19.6.19

Work is progressing well as our project takes shape. It’s week 17 of the 77 week programme and the steel frame is going up for Block A. Approximately 35 per cent of the overall steel frame has already been erected in only four weeks. You can view more project progress images on our timeline page.